Cape City Mayor Geordin Hill-Lewis on Thursday, 29 June, inspected progress on the R715 million Cape Flats Bulk Sewer improve which is able to profit 300 000 households primarily in decrease earnings neighbourhoods within the metro. The Metropolis is on monitor to finish the total 28kms of pipeline rehabilitation by 2025, making this South Africa’s largest sewer improve challenge.
Communities benefitting from the Cape Flats sewer upgrades embrace Athlone, Hanover Park, Lotus River, Ottery, Grassy Park, Eagle Park, and areas round Pelican Park, amongst others.
‘Officers on the bottom upgrading the Cape Flats Bulk Sewer inform me we’re on monitor to finish this mega challenge by 2025. We’re placing R206m behind this improve in 2023/24 to verify we get this completed.
‘With this historic challenge – the most important ever undertaken in democratic South Africa – we’re upgrading bulk sewers first constructed on the peak of apartheid within the 1960’s, and future-proofing these for the following 100 years to the advantage of future generations of Capetonians. After we speak of our long-term imaginative and prescient of a constructing a metropolis of hope for all, it actually comes all the way down to bread and butter tasks like this, which result in higher residing circumstances for residents,’ mentioned Mayor Geordin Hill-Lewis.
Over the following three years, the Metropolis will make investments a large R1,3bn in main bulk sewer upgrades to the Cape Flats, Philippi, Milnerton, and Gordon’s Bay strains.
‘For the brand new monetary 12 months, roughly 73% of Cape City’s infrastructure price range – or simply over R8bn – will go in direction of important upgrades benefitting lower-income households, casual settlements, and poorer communities in our metropolis.
‘In addition to the enhancements to fundamental companies, and private and neighborhood dignity, the size of Cape City’s R43bn three-year infrastructure pipeline – greater than Joburg and Durban mixed – will create an estimated 135 000 jobs within the metropolis over three years,’ mentioned Mayor Hill-Lewis.
Revolutionary tech behind sewer improve
A bulk sewer is sort of a freeway for sewage. This sort of pipe carries excessive volumes from a large space in direction of the remedy works.
‘To finish the Cape Flats improve, the Metropolis is utilizing progressive trenchless expertise, which ensures that there aren’t any prolonged and disruptive excavations whereas work is underway.
‘Residents and companies should not inconvenienced by invasive development websites within the space, and the one seen indicators that upkeep work is being carried might be within the type of some employees and autos at manhole entry factors. This methodology can be roughly thrice less expensive than standard excavation development work,’ mentioned Councillor Zahid Badroodien, Mayoral Committee Member for Water and Sanitation.
Throughout the web site go to, officers showcased varied progressive tech. Pipelines – that are 4 metres underground – are first profiled by a robotic crawler utilizing lasers to document the state of the within of the pipe. Information is distributed to officers above floor who’re capable of decide precisely which methodology to make use of to repair the pipeline in probably the most cost-effective approach.
There are three overarching strategies of Trenchless Know-how – specifically, Cured In Place Pipe (CIPP) lining, Calcium Aluminate Cement (CAC) and Spirally Wound Liner (SWL) – and every might be thought of when deciding on one of the best rehabilitative answer for various sections of the pipeline.
Cape City quadrupling sewer pipe substitute
Throughout the metro, the Metropolis is on monitor to exceed its goal of doubling sewer pipe substitute to 50km for the 22/23 monetary 12 months ending June 2023. That is a part of a significant sewer pipe focus which is able to see 100km being changed yearly throughout the metro, for a complete funding of R850m over the following three years.
Pipe substitute is a part of a technique to convey down sewer spills over time, together with main bulk sewer upgrades, proactive cleansing of sewer strains, resourcing of sewer spill response groups, and digital telemetry programs for early warnings on sewer spills.
These interventions have led to a 30% downward development in reported spills in cape City during the last two years primarily based on preliminary knowledge. The Metropolis is now rolling out a Reactive Incident Administration System (RIMA) to trace progress much more carefully by digitising the coordination of sewer spill responsiveness.
For 2022/23, the Metropolis is executing 36 pipe replacements, with 22 full and 14 set to complete earlier than the top of the monetary 12 months on 30 June.
Sewer pipe substitute tasks making up the 50km goal for the 2022/23 monetary 12 months (ending 30 June):
· 1 Main Bulk Rehab challenge – Cape Flats Bulk Sewer Rehabilitation
· 22 Accomplished tasks – Bishopscourt, Southfield, Constantia, 2x Bergvliet, 2x Kuils River, Strand, Tokai, Bellville, Dennedal, Delft, Milnerton: Joe Slovo/Phoenix, Milnerton: Dunoon, 4x Gugulethu, 4x Makhaza.
· 14 tasks at the moment in execution – Dennedal, Candy Valley, Nova Constantia, 2x Strand, Scottsdene, Maitland, Uitsig, Epping, Bellville: Boston, Bellville: De La Hey, Bellville: Welgemoed, Durbanville, Gugulethu.
Deliberate tasks to fulfill the large goal of 100km of sewer pipe substitute for 2023/24 (beginning 1 July):
· Brackenfell Industrial, Stikland Industrial, Kraaifontein Industrial and Bellville: Welgemoed. Bergvliet, Muizenberg, Lotus River, Constantia, Tokai, Wynberg, Broadlands, Strand, Kuils River, Mission Grounds/Sir Lowry’s Go, Tuscany Glen, Eerste River South, Kraaifontein, Eversdal, Brackenfell, Bellville, Brackenfell Industrial, Dunoon, Joe Slovo, Langa, Philippi: Samora Machel, Crawford/Lansdowne, Uitsig, Bakoven/ Camps Bay, Ravensmead, Rondebosch, Gugulethu, Parow Industria, Avondale, Parow, Bishopscourt, Clifton, Lansdowne, Athlone, Claremont, Decrease Crossroads, Bridgetown, Fresnaye.